Three things in one place: what is being dug up on your street, where the big projects actually stand, and a search of the Town’s own planning papers. Every fact here links back to the page it came from, in the Town’s words, so you can check it yourself.

Read this first. This is my campaign’s tool, not the Town’s, and it is not legal advice. The two “sides” below are meant to be one-sided — that is the point of them. Short summaries can be wrong or out of date. Before you rely on anything here, click through and read the real page it came from.

The Terminals — the grain building on the harbour

The big concrete grain building on the water. The Town bought it in 1997, it has sat empty for decades, and since 2022 the Town has been working with two development companies on a plan for the site. Nothing has been built and the building is still standing.

200020052010201520202025today

Point at a dot to see what happened that day. On a phone, use the buttons.

15
30 years from the first written record to today, and 15 steps in between. Every one is listed below, in the Town’s own words.

Where it stands today

Agreements and planning permission. Council told staff to sign the binding agreements in June 2024, and a schedule received by council in September 2025 runs to May 2027 — planning applications in March 2026, council considering them in December 2026, site plan approval in 2027. The Town's own project page shows nothing dated 2026, so whether that March 2026 step happened is not published. No council has ever voted to demolish the building.

  1. 1996
    A study landed

    Engineers checked the building's structure — a year before the Town even owned it.

    Show me where it says that
    “A structural assessment was undertaken in 1996 of the Terminals which identified no significant structural concerns.”

    Collingwood Waterfront Master Plan, Town of Collingwood

  2. 1997
    Land

    The Town bought the grain building and the land it sits on.

    price not published

    Show me where it says that
    “The Town of Collingwood purchased the Terminals in 1997”

    History of the Grain Terminals, Town of Collingwood

  3. June 2018
    A study landed

    Engineers checked the building and said it is sound, then priced both fixing it and knocking it down.

    repair $8M to $9.7M · demolition about $5M

    Sources disagree. These are a consultant's estimates and a consultant's recommendation. No council ever voted on either number.

    Show me where it says that
    “From a macro perspective, the structure is sound.”

    Collingwood Terminals Engineering Condition Assessment, Tacoma Engineers

  4. 31 October 2019
    Staff suggested

    Town staff wrote a paper setting out every possible future for the building, with a price on each, and suggested the Town go looking for a partner or a buyer.

    called an $8M unfunded bill · about $46,000 a year to keep as it was

    Show me where it says that
    “the Town move beyond brainstorming and seek partners or buyers”

    Collingwood Grain Terminals White Paper, Town of Collingwood

  5. August 2020
    A study landed

    Engineers checked the wooden posts holding the building up and said they are strong enough to keep holding it up.

    Show me where it says that
    “the piles are currently in a condition that provides structurally adequate support for the Terminal facility above.”

    Collingwood Terminals Foundation Pile Assessment, Tacoma Engineers

  6. 2021
    Council decided

    The Town put out a public call asking companies to send in ideas for what to do with the building.

    Show me where it says that
    “In 2021, Town staff went to tender to find a potential partner to work with the Town on the revitalization project.”

    Terminals Point Project, Engage Collingwood

  7. 2022
    Council decided

    Council agreed on sixteen rules that any deal about the building would have to follow.

    Show me where it says that
    “Council approved a set of 16 Guiding Principles to form the basis of a partnership.”

    Terminals Point Project, Engage Collingwood

  8. August 2022
    Council decided

    The Town picked two development companies, Streetcar and Dream, to work with.

    Show me where it says that
    “In August 2022, Streetcar and Dream was chosen as the successful company for this partnership”

    Terminals Point Project, Engage Collingwood

  9. 27 March 2023
    A study landed

    The two companies showed council their pictures and ideas for the site. Council listened; nothing was voted on that night.

    Show me where it says that
    “Streetcar Developments Inc and Dream Unlimited Corp (Streetcar and Dream) presented their vision”

    Grain Terminals Plan Unveiled, Town of Collingwood

  10. 19 June 2023
    Council decided

    Council agreed to sign a first, not-yet-final agreement setting out who would own and pay for what. Under it the Town would sell about a fifth of an acre, lease about four fifths of an acre long term, and keep about twenty acres.

    the Town's costs in that agreement worked out to $15,055,777 in 2022 dollars

    Show me where it says that
    “The Present Value of the costs to the Town … is $15,055,777.”

    Terminals Point Project, Engage Collingwood

  11. 15 November 2023
    Council decided

    After a public vote on four choices, the project got a new name: Terminals Point.

    Show me where it says that
    “Project name, 'Terminals Point', announced November 15, 2023”

    Terminals Point Project, Engage Collingwood

  12. 17 June 2024
    Council decided

    Council told Town staff to go ahead and sign the final, binding agreements with the two companies.

    Sources disagree. No public source shows those agreements were actually signed afterwards, or that any land has changed hands.

    Show me where it says that
    “Council approval for the Town project team to execute the Definitive Documents with Streetcar & Dream”

    Terminals Point Project, Engage Collingwood

  13. 9 June 2025
    A study landed

    Council got a report saying both sides had finished checking the site and the numbers, and both were content to carry on.

    Show me where it says that
    “According to Staff Report CCS2025-03, the due diligence period for the project has officially concluded”

    Terminals Point Project, Engage Collingwood

  14. 3 September 2025
    A study landed

    Council received a new timetable. Under it the planning permission applications go in by the end of March 2026, council considers them in December 2026, and the last approval on the list comes in May 2027.

    Show me where it says that
    “THAT Staff Report CCS2025-05, Terminals Point– Project Schedule Update, be received for information.”

    Staff Report CCS2025-05, Terminals Point Project Schedule Update

  15. 3 December 2025
    People were asked

    The Town and the companies held an online meeting about the private building part of the site — about one acre out of twenty.

    Show me where it says that
    “Learn about the proposal for the private development site of Terminals Point.”

    Terminals Point Project Virtual Open House, Town of Collingwood

What nobody has published yet

  • What the Town paid for the building in 1997. No source gives a price.
  • Whether the binding agreements council told staff to sign in June 2024 were ever signed, and whether any land has been sold or leased.
  • Anything at all dated 2026. The Town's project page lists no 2026 event, so whether the March 2026 planning application went in is not published.
  • What the Town has spent in total on studies, upkeep and the project team. The most recent figure anywhere is about $46,000 a year, from 2019.
  • The widely repeated figure of about $200 million for the whole redevelopment. It appears in news coverage and on Wikipedia, in no Town document I could find, and it would be the companies' money rather than the Town's. It is not on this page because I could not source it.
  • When grain handling actually stopped. The Town's own history says the last rail cars were filled in 1986; the Town's project page says the building has been unused since 1993.
  • The minutes and recorded votes. Four of the council decisions above come from the Town's own summary of them on its project page, not from the minutes, which would not load.

Researched from the Town’s own pages and council material on 18 October 2026. Every quote is copied word for word and links to where it is written. This is my campaign’s page, not a Town of Collingwood product, and the record is still moving — check the links before relying on anything here. If I have something wrong, tell me and I will fix it and say that I did.