Construction Projects (Town of Collingwood, read 18 October 2026)
PDF page 1
Town's engineering standards and to provide active transportation opportunities along the corridor. Construction is tentatively scheduled for 2027, subject to Council approval. Peel Street Reconstruction Newsletter - May 2025 Second Street and Oak Street Canal - Bridge Improvements Bridge 08 (Oak Street culvert) and Bridge 09 (Second Street bridge) both convey the Oak Street Cana…
Read it yourselfOriginal document
Construction Projects (Town of Collingwood, read 18 October 2026)
PDF page 1
Sixth St. to Seventh St. Seventh Street: Spruce St. to Walnut St. Spruce Street: Sixth St. to end south of Tenth St. Tenth Street: Oak St. to Clarkson Crescent Watts Crescent Fifth Street: Spruce St. to High St. Maple Street: First S…
Read it yourselfOriginal document
Construction Projects (Town of Collingwood, read 18 October 2026)
PDF page 1
at the right time, it can extend pavement life by six to eight years or more. Road Sections include: Pretty River South Connell Street Ron Emo Road – Sanford Fleming Drive to Raglan Street Sanford Fleming Drive – Sixth Line to North End Sixth Line - Poplar Sideroad to North End Road Resurfacing Works will include removing exis…
Read it yourselfOriginal document
Town of Collingwood Official Plan
PDF page 150
Concept as defined by the regulatory flood shall regulate the Silver Creek, Black Ash Creek, Townline Creek and Batteaux River and Oak Street Canal floodplains. c) In addition to the permitted uses identified within the Environmental Protection Designation or within the regulatory floodplain of the Oak Street Canal, existing uses…
Read it yourselfOriginal document
Construction Projects (Town of Collingwood, read 18 October 2026)
PDF page 1
…west side of Collingwood is part of this project as well. Active Transportation facilities were evaluated as part of the design, and one (1) way cycle tracks will be constructed on each side of Sixth Street from Hurontario to High Street. Construction will be in two (2) phases: Phase 1 Hurontario Street to Oak Street, and Phase 2 Oak Street to High Street. Phase 1 construction is scheduled for 202…
Read it yourselfOriginal document
Staff report P2023-32, adoption of the Official Plan
PDF page 6
change to the classification of Third Street as a collector road must be supported by expert analysis, ideally through the Transportation and Mobility Master Plan (see next Section of this Report on “Transportation”). The 2023 Capital Bud…
Read it yourselfOriginal document
Sixth Street Reconstruction (Town of Collingwood project page)
PDF page 1
improving overall canopy quality and resilience. Project News & Updates May 7, 2026: Temporary Road Closures and Transit Disruptions - Revised As part of the next phase of the Sixth Street Reconstruction Project, a temporary disruption will be in effect starting May 11, 2026. Below are details, including projected timelines, and impacts to transit service. The intersection of Hur…
Read it yourselfOriginal document
Construction Projects (Town of Collingwood, read 18 October 2026)
PDF page 1
new sidewalks; asphalt paving of the roadway; restoration of driveways and boulevards; bridge repairs and upgrades between Oak Street and Birch Street. Please see Notice of Construction in the pdf file provided below for further details. Notice of Construction - June 2025 Construction of this project has been completed an…
Read it yourselfOriginal document
Construction Projects (Town of Collingwood, read 18 October 2026)
PDF page 1
…orth bridge work and watermain installation. Bridge work is ongoing through the 2025/2026 winter and road work will begin in the spring of 2026 after the half load restrictions have been lifted. Peel Street Reconstruction - Hume to Bush Detail design is underway and expected to be completed in 2026. The general scope of the work consists of the reconstruction, urbanization, and drainage improvemen…
Read it yourselfOriginal document
Sixth Street Reconstruction (Town of Collingwood project page)
PDF page 1
sewer replacement, watermain replacement, streetlights, traffic signals at Hurontario Street/ Sixth Street and Hurontario Street/ Hume Street intersections, Oak Street bridge works, road reconstruction, installation of cycle tracks, and resto…
Read it yourselfOriginal document
Sixth Street Reconstruction (Town of Collingwood project page)
PDF page 1
will have temporary detours (refer to the map for details). Visit the Transit Page for more information. Blink Route West Route Crosstown East Route The stops at Sixth and Hurontario Streets (Stop #602), and Hurontario and Ste. Marie (Stop #206) will not be serviced during the road closure dates. Image Your anticipated patience is appreciated. Future updates will be shared as they…
Read it yourselfOriginal document
Construction Projects (Town of Collingwood, read 18 October 2026)
PDF page 1
East (Ste. Marie Street to Ste. Paul Street) Sanitary Renewal Project This project involved full reconstruction with new sanitary sewer including services to the property line, new watermain upgrades including service…
Read it yourselfOriginal document